CIDCO
  
  

 
 

Engineering Department Chart
Engineering Department at a Glance with Jurisdiction
Tenders
Registration of Contractors
Water rates in Navi Mumbai
Water supply procedure and check list
Drainage NOC

 

  Electrical NOC for Kharghar

 
POWER SUPPLY INFRASTRUCTURE DEVELOPMENT CHARGES (PSIDC) KHARGHAR NODE


Background

MSEB presently known as MSEDCL was not in a position to develop power supply infrastructure in Kharghar area matching with development envisaged by CIDCO in Kharghar. To avoid mismatch between development and availability of infrastructure CIDCO entered into an agreement with MSEB on 1-8-2003 with the objectives of -

a) Power supply distribution infrastructure to plotholders on demand.

b) To derive and apply uniform rate for power supply distribution infrastructure.

c) To provide single window clearance.

Responsibility shouldered by CIDCO consists of providing 33 kV feeder line , 33/11 kV receiving station , 11 kV network, distribution transformer station and LV distribution network. This agreement covers the area from sector-1 to 24 of Kharghar node . Validity of the Agreement is upto July,2010.

As on April,2007, CIDCO has completed the work of installation of 20 MVA capacity, 33/11 kV sub-stn. , 8 K.M of 33 kV feeder 15 MVA capacity , 11/0.4 kV distribution sub-station and 40 Km of 11 kV feeder line besides LV network and 92 kms LV network and work is in progress. This means completion of 25 % of the work planned.

The expenditure in providing power supply infrastructure in proportion is recovered as PSIDC from plot holders.

What is PSIDC ?
PSIDC means power supply infrastructure Development Charges. It is a proportionate cost incurred for providing power supply infrastructure from 33/11 kV receiving stations to either upto 11/0.4 33kV sub-station or upto metering point to be recovered from plotholders as per the approved policy. It is applicable only to sectors 1 to 24 in Kharghar node.

PSIDC charges -

I) Categorization

The plot holders are categorized on following basis:
a) Plot size X FSI , if it is less than 4000 sq.mtr.
b) Plot size X FSI , if it is equal or more than 4000 sq.mtr.

II) Payment of PSIDC charges
( prevailing as on June,07)
a) For category I (a) i.e. where plot size X FSI is less than 4000 sq.m. at above rate will be Rs. 350/- per sq.mtr. and formula for PSIDC will be
PSIDC = Plot size x FSI x 1.35 xRs.350/-

b) For category I (b) i.e. where plot size X FSI is equal or more than 4000 sq.m. at above rate will be Rs. 225 /-per sq.mtr. and formula for PSIDC will be PSIDC = Plot size x FSI x 1.35 x Rs.225/-

Further, for category (Ib) developer will be required to construct sub-station as per MSEDCL’s norms and will also be required to pay necessary supervision charges and other charges directly to MSEDCL.

III) Amalgamation
In case of amalgamation of plots the procedure will be as follows -
If the developer would amalgamate adjacent smaller plots falling in category-1(a) at above by amalgamating adjacent plots thereafter completion of development in one plot can apply for power supply connection of the completed building and in such case he will be required to pay charges at Rs.350/- per sq.mtr.(prevailing rate as on June06) as applicable to LT connection etc. as per formula at 2(a) above even if permissible BUA is equal or more than 4000 sq.mtr. for amalgamated plots. The developer would be required to construct sub-station while developing 2nd plot and at that time the recovery will be effected as per formula 2 (b) above and credit will be given for amount already paid by developer in earlier instance. However, the cost of LT cable in respect of earlier plot will be debitable to developer. ATPO should ensure that completion certificate for amalgamated plot is issued only after construction of sub-station.

IV) Steps for availing power supply to plotholders in sector-1 to 24 kharghar
1) Payment of PSIDC as per formula -
a) For all agreement s after 1st Jan’06 payment to be made at the time of
allotment, with Marketing Section.

b) For all agreement prior to Jan’06 , payment will be collected at single
window Kharghar at the address given below separately.

2) Approach single window with a payment receipt & agreement for obtaining NOC to Building Permission Deptt. For issue of commencement certificate and occupancy certificate.

3) Approach single window with details listed below -
a) Commencement certificate and occupancy certificate.

b) Copy of A1 & D1 form indicating the power requirement in KW
(sample copy enclosed).

c) No. of meter rooms and no. of meters in each meter room.

d) Details of the meter room.

e) Name of the agency executing the electrical work.

f) MSEDCL Scheme sanction letter for plotholders with buildable area
4000 sq.mtr. or more with sub-station. 

g) Permission of Electrical Inspector for charging sub-station.

h) Provision made in the plot for power/distribution cables.

i) Payment of service charges, security deposit and meter charges as
per MSEDCL’s prevailing rate.

NOTE
The LT cable laying work shall be completed within 20 days and HT cable within 30 days after submission of Occupancy certificate to the CIDCO Electrical Deptt.( single window) office Kharghar subject to the submission of documents listed above in normal course.

Single Window System
Single Window Office has been established at plot NO.21, sector-4, Kharghar where MSEDCL and CIDCO’s officials are available for assisting the plotholders in obtaining the power supply connection .

Other assistants available at Single window office are -
· Redressal of grievances regarding power supply .
· Payment of Energy bills.
· Complaint about non-working of street lights.

Name & Addresses of MSEDCL and CIDCO officers

CIDCO Ltd

Name

Designation

Address

Phone / Mobile

Shri J.R. Nayak

SE(Elect.)

6th flr, CIDCO Bhavan ,CBD-Belapur, Navi Mumbai

67918628

Shri K.J.Sankhe

EE(Elect.)

As above

67928618(o)

9821192152

Shri T.L. Parab

AEE(Elect)

Single window office ,sector-4, Kharghar

27742795 (o)

9869828835

Shri N.U. Nemade

AE(Elect.)

As above

27742795

9969285839

MSEDCo. Ltd.

Shri N.B. Wadekar

EE(PNL)

Urban Divison

o/o.EE,MSEDCL

Bhingari,Panvel

27490299

9820366853

9320366853

Shri M.N.Munge

Dy.EE

o/o.Dy.EE,

MSEDCL, Kalamboli sub-divn.PL-6, A/5,sector-1, Khanda Colony

27466450

27462024

9869036587

Shri D.N. Hipargekar

J.E.Sect-1 to13,21to23, 25, 29 to 31, 35,36,44

o/o.J.E.MSEDCLsingle window office, Sector-4, Kharghar

27742795

Shri U.D. Bhagwat

J.E.Excluding above sectors

o/o.J.E.MSEDCL33/11 kV sub-stn.sect-19,Kharghar

22917943

9870059698

Top

Press Release